Brunswick Street Station Refurbishment
|
The Project
![]() ![]() go card ticketing equipment changes at Brunswick Street station from Saturday 08 March 2008. The upgrade work at Brunswick Street station will affect go card passengers.
Note: There will not be a fare machine until the upgrade works are nearing completion. Top up is also available:
For more information call Translink on 13 12 30.
Platforms 3 and 4 will be operational from 31 March 2008 and Platforms 1 and 2 will be closed. In June 2007, construction work commenced on Stage 1 of the Brunswick Street Station Refurbishment Project and will continue until its completion in December 2008. Stage 2 of the Brunswick Street Station Refurbishment will feature the construction of a new lift, stair and escalator to each of the platforms, improved lighting, a new ceiling above the platforms, and better seating to platforms 1 & 2. It will also see the completion of the new concourse level and an emergency escape. Platforms 3 & 4 will be operational from the 31st March with Stage 2 involving the closure of platforms 1 and 2 resulting in impacts for the travelling public who utilise Brunswick Street Station. For further information visit the Customer Information Booth on the concourse at Brunswick Street station or phone 1800 643 443.
Travelling to Brunswick Street Station
Funded by the Queensland Government through TransLink, the Brunswick Street Station Refurbishment is an upgrade project which will transform the station into a more accessible, attractive and safe destination and departure point for QR Citytrain passengers.
Construction began on 14 July 2007 and the platforms, lifts and escalators will be operational by December 2008. QR Citytrain is working with the Valley Metro Centre, located above the station, and the local community to keep stakeholders informed and impacts from the project to a minimum. QR Citytrain will advise passengers throughout the life of the project of alternative routes to complete their journeys to Brunswick Street Station.
Integral part of the Valley As such, QR Citytrain has a vital role to play. The station will be revamped to reflect the culture of the Valley and the artist's impression above demonstrates this open and contemporary design. QR Citytrain will engage local artists and schools to assist with the artwork in the station.
|